Construction progress · charts

528 Town Center

Aerial progress logs TC528‑001 (Sep 7), TC528‑002 (Sep 11) and TC528‑003 (Oct 6) and TC528‑004 (Oct 31, 2026) · Tannos Development Group · FM 528 at Clear Creek · TDB Solutions LLC

Site development phases

Visual % complete · hover for notes
Complete by Sep 7Gained by Sep 11Gained by Oct 6Gained by Oct 31Remaining

Build-out by flight

Overall build-out (sitework 20% / vertical 80%) and sitework complete, at each flight.

Sitework completeOverall build-out

Program started, by use

Square feet on parcels with any work as of Oct 31, against the developer's program of record.

Work underwayNot started

Parcels with work underway

Every parcel showing activity in any flight
Sep 7Gained by Sep 11Gained by Oct 6Gained by Oct 31

Parcel register

Highlighted rows moved since Oct 6
ParcelProgramStatus Oct 31Oct 31Oct 6Sep 11Sep 7ConfidenceObserved Oct 31

What changed

Oct 6 → Oct 31

  • Retail 4 steel complete and roof-decked — metal deck now covers the whole footprint with guard framing at the roof edge; no wall panels yet.
  • Retail 5 slab poured and steel rising — the second building slab on site, with columns and beams going up and more steel staged beside it.
  • Other white concrete is parking lot, not building slabs; Retail 1, 2 and 3 are still pads.
  • Earthwork continues on the open pads with a crawler crane and excavators working.
  • Apartment wing — the work at the back is pond retention wall, not piling; no foundations or framing started.

Sep 11 → Oct 6

  • Retail 4 steel framed across the full footprint — columns, beams and joists the whole length of the slab; no deck, walls or envelope yet.
  • Retail 5 from bare cut to footing layout — footing pits dug, stake and string lines set, lumber and rebar staged.
  • Retail 3 pad fine-graded with a dozer on it and silt fence along the edge.
  • Retention-wall work back at the pond beside the apartment wing's east side.
  • New trench runs and site trailers beside Retail 2; fresh earthwork at the east office block.

Sep 7 → Sep 11

  • Retail 4 slab complete and steel columns set building-wide, roof framing over the west third.
  • Precast storm structures delivered; site office trailer set on the frontage.

Open items

  • Retail numbering — parcels are numbered 1 to 5 from west to east to match the 360° tour. The Sep 7 and Sep 11 logs lettered them A to E with the steel building on C; their readings are carried here under the tour numbers. Please confirm against the developer's plan.
  • Which site plan governs — one drawing shows a hotel and entertainment complex; the dimensioned plan at 733,100 SF shows neither.
  • Project name — 528 Town Center on the plan sheet, Friendswood City Center in marketing.
  • Oct 31 figures — estimated from a single-day flight; utilities, drives and ponds were not re-measured and repeat Oct 6.
  • Phase target dates — without them this log shows progress, not schedule variance.

Percent-complete figures are visual estimates from aerial imagery compared against the developer's site plan, not certified quantities. Overall build-out weights sitework at 20% and vertical construction at 80%. The 24 September and 31 October 360° surveys are carried in the viewer; Oct 31 percentages are estimated from that flight's imagery and were not field-verified. For progress documentation and marketing use, not pay applications. TDB Solutions LLC · Houston, TX · FAA Part 107.